The 2024 bond included funding for improvements to Crestwood Elementary, which was originally built in the 1990s.

Current Status: Planning

Project details:

  • Modernizing front office and security vestibules
  • Installing access controls
  • Installing teaching walls to classrooms
  • Studying traffic and student pickup and drop off facilities for safety

Timeline:

  • Planning, design & permitting: 2025-2026
  • Construction: 2026-2027
  • Estimated completion: Late fall 2027

Budget: 

  • $2.9 million

Project Team

Architect: Studio Meng Strazzara 

Mechanical/Electrical Engineer: Hargis